THE first section of new rail track has been laid on Inland Rail’s Illabo to Stockinbingal project, marking a major milestone as construction gathers momentum across...
A 450-TONNE crane has arrived in Junee to lift additional sections of Kemp Street’s new pedestrian footbridge into place. According to Inland Rail’s latest out-of-hours works...
ALL 16 concrete girders have now been installed on Junee’s new Kemp Street bridge, closing the gap over the rail corridor and giving locals the clearest...
THE 700-tonne crane used in last month’s aborted Kemp Street bridge operation has returned to Junee, setting the stage for a massive weekend of construction across...
THE wait for Junee’s new Kemp Street bridge has blown out from 18 months to two years, despite repeated assurances from Inland Rail that the project...
JUNEE will be reduced to just one crossing over the rail corridor next weekend as major upgrades are carried out at the Olympic Highway underpass. The...
INLAND Rail has confirmed the installation of concrete girders on Junee’s new Kemp Street bridge has been paused while an urgent safety reassessment of the lifting...
A MAJOR operation to install the concrete girders for Junee’s new Kemp Street bridge has ground to a halt after just one of the 16 enormous...
A 700-TONNE crane has rolled into Junee as Inland Rail crews prepare to install the massive concrete girders that will support the deck of the new...
THE first sections of the pedestrian footbridge that will run alongside Junee’s new Kemp Street bridge have been lifted into place, marking another major milestone in...